Project Engineering & Project Management
Taak;
Project Management - Upgrade dryers en upgrade zoning total plant
Projecten;
Reinforcement dryers and new hygenic zoning building East and West
Beschrijving;
> Upgrade plant West Nutricia. New hygienic zoning
> Upgrade plant Oost Nutricia. New hygienic zoning
> Upgrade dryers T1 and T2 at Nutricia. New strenghtness and reinforcement the dryers
> Project Management and Engineering eparation everything for the pitstop week Nutricia
> Site management pitstop weeks on site at Nutricia
> Site management update zoning plant West Nutricia
Verantwoordelijk voor;
Specifications, plan, costs in the Nutricia/Danone proces; Jalon, PRS, URS, FRS, shutdown, tests, start production!